Construction Update
One Canal
Dubai Water Canal
We are delighted to provide you with an update on the progress of One Canal, to showcase the milestones achieved and anticipated developments ahead.
Progress Status
One Canal
Progress Status

Design
Concept Design
Completed
Schematic Design
Completed
Shoring Design
Completed
Detailed Design
Completed
IFC Drawings
Completed

Procurement
Shoring Contractor
Appointed
Piling Contractor
Appointed
Main Works Contractor
Appointed
MEP Contractor
Appointed
Facade Contractor
Appointed
Fit Out Contractor
Appointed

Authority
Preliminary Design Approval
Obtained
Design NOCs Approval
Obtained
Site Clearance NOCs
Obtained
Shoring Permit
Obtained
Piling Permit
Obtained
Building Permit
Obtained

Siteworks
Shoring Works
Completed
Piling Works
Completed
Raft Foundation
Completed
Substructure Works
Completed
Superstructure Works
Completed
External Glass Works
In Progress
MEP and Finishes Work
In Progress
Site Landscaping
In Progress
Interior Fit-Out
In Progress
Facade Installation
In Progress
Project Handover
Upcoming
Updated Timeline

Shoring Works
Completed
Piling and Enabling
Completed
Foundation / Raft Works
Completed
Substructure Works
Completed
Superstructure Works
Completed
External Glass Works
Q3 2026
MEP and Finishes Work
Q3 2026
Handover
Q4 2026
Thank You